调试,debugging
1)debugging[英][di:'b?g][美][di'b?g]调试
1.Design and Debugging of Axis Z Servo System Controlled by UMAC;UMAC控制下Z轴伺服系统设计与调试
2.Debugging and commissioning of a 3800m~3/h air separation unit;3800m~3/h空分设备调试及投运
3.Design and Debugging of NC Double Sided Drilling Custom-built Machine;数控双面钻窝专用机床设计及调试
英文短句/例句

1.Test of co-whole system整架调试(整机联试)
2.&Debugger Options...调试器选项(&D)...
3.Installs the Debugger Interface for stored procedure debugging.安装调试程序接口以调试存储的过程。
4.Unable to start debugging. A program to debug has not been specified.无法启动调试。尚未指定要调试的程序。
5.Do you want to debug using the selected debugger?是否希望使用选定的调试器进行调试
6.Warning: A kernel debugger is present. Launch Debugger?警告: 存在内核调试器。启动调试器吗?
7."The commissioning shall consist of single commissioning, cold commissioning and hot commissioning. "调试应该包括单机试车、冷试车和热试车。
8.&Debug source path:调试源代码路径(&D):
9.&Compile with debug Info编译带调试信息(&C)
10.microprogrammed system debugging微程序控制的系统调试
11.simulator debug utility模拟程序的调试应用
12.run-time debug symbol table运行时期调试符号表
13.Include &remote debug symbols包含远程调试符号(&R)
14.package debug aid system程序包调试辅助系统
15.I'll show you how it works.我可以调试给你看。
16.debugging period调试时间排除故障时间
17.Debugger Event Log Properties调试器事件记录属性
18.missetting of specimen试样未调准, 试样误调
相关短句/例句

commissioning[英][k?'mi??n][美][k?'m???n]调试
1.A case of commissioning and trouble shooting of DCS for evaporator station;蒸发站DCS系统调试及故障排除
2.Commissioning and Operation of Determination of Arsenic by AFS-230E Atomic Fluorescence Spectrometer;AFS-230E原子荧光光度计测定砷的调试和使用
3.Commissioning and operation of 60000 m~3/h air separation units at Wugang: a summary;武钢H台60000m~3/h空分设备投产调试总结
3)debug[英][,di:'b?ɡ][美][di'b?ɡ]调试
1.Debugging the hydraulic station of hoist braking system in a shaft;矿井提升机制动系统液压站的调试
2.Sumup of 14000m~3/h Air Seperator Plant Introduced From Hangzhou in Installation and Debugging;杭氧14000m~3/h空分装置安装调试中的问题与处理
3.Simple Talking about Debug and Control of Asphalt Concrete Mixing Quality on Freeway;浅谈高速公路沥青混凝土拌和质量的调试和控制
4)adjustment[英][?'d??stm?nt][美][?'d??stm?nt]调试
1.Technical analysis of the process in the adjustment of end thickening tube production;加厚管生产的调试过程技术分析
2.Installation and adjustment of heptafluoropropane fire-extinguishing system;七氟丙烷自动灭火系统的安装与调试
3.Large Machining Equipment Installation and System Adjustment;大型机加工设备的安装及系统调试
5)test[英][test][美][t?st]调试
1.Analysis of problems with the installation and test of tubular hydro-unit;灯泡贯流机组安装调试中几个问题的分析处理
2.Retrofit,service and test of CNG buses;CNG客车的改装、维修及调试
3.Engineering Interface of Type LKD1-T Train Control Center and the Site Testing Method;LKD1—T型列控中心的工程接口和现场调试方法
6)commission[英][k?'m??n][美][k?'m???n]调试
1.Maintenance of Equipment and System during Installation and Commission of Nuclear Power Plants核电厂安装和调试期间设备和系统的维护保养
2.The commissioning and operation codes of the CFB boilers were discussed and summarized.总结了启动燃烧器和冷渣器的调试规范和锅炉的启动操作要领。
3.During the whole process of integrated commissioning stage of Zhengzhou Gas Power Plant which installed with 2×390 MW(Siemens GUD1S.本文就试运过程中发生的非正常停机事件进行了分析,为避免同类事件再次发生,亦为今后机组调试奠定基础。
延伸阅读

调试调试commissioning  岛进行试脸,包括对主燕汽系统的温度调节试验、汽轮发电机冲转试验、给水系统试验、电动和汽动给水泵试验等。通过试验,可以及早发现、并有较充裕的时间解决汽轮发电机组存在的问题。如不采用调试锅炉,则常规岛试验的关键步探均要较采用调试锅炉时适当推迟(如首次冲转要推迟到首次临界后二至三周)进行. 热态功能试验为第四子阶段。本阶段的试验目的是:在冷态和热态停堆状态的温度和压力的全范围内对核燕汽供应系统的有关设备和系统的功能响应、耐久性、安全性进行验证,以保证它们能按设计要求运行;通过验证使某些运行规程和定期试验程序生效;使运行人员熟悉电厂的运行。 试脸的前提条件是:堆内构件安装完毕,压力容器顶益就位,反应堆冷却剂系统压力边界上的保温层完整,对在热态功能试验期间要用到的部件和辅助系统所有必需的试验和检查已完成;进行试验所必需的辅助系统投运或可用;流体供应系统可用;对某些部件、装t以及安全保护系统虽然可能没有严格的要求,但它们必须对本阶段试验可用。 进行试验时,使用相关的运行规程使核蒸汽供应系统达到热停堆状态,方法是用主泵使反应堆冷却剂分若干步升沮.先用余热排出系统控制温度,当温度达到该系统的上限值时,用汽机旁路系统对空排放控制温度。系统内的压力在德压器内形成汽腔之前是通过化学与容积控制系统中上充泵经上充和下泄管路控制的.在汽腔形成之后,压力是由稳压器中的电加热器和喷淋装t控制的。 在反应堆冷却剂加热期间和在热停堆工况下对管路和部件的位移进行目视检查和侧童,使其与支承件之间不致因约束过紧或过松而造成不可接受的形变;验证仪表和控制、允许和禁止互锁的正确性;检查和调整反应堆保护和控制通道;验证稳压器的加热器和喷淋装t的性能;检验稳压器压力和水位的整定值以及超压保护动作的正确性;检验燕汽发生器安全阀的整定值;检查控制棒驭动机构(不带控制棒)及相关的通风系统运行的正确性,检查保温层,对辅助系统(化学和容积控制系统、余热排出系统、核岛设备冷却水系统、核取样系统、燕汽发生器排污系统、反应堆翻和水补给系统、核岛排气疏水系统等)进行性能和运行方面的试验;进行核辅助厂房和反应堆厂房通风系统试验、应急备用电源配电(在厂外电源丧失之后)试验、在额定压力和沮度下辅助给水系统首次供水试验;检验在热停堆状态下安全注射系统和辅助给水系统运行的正确性;在向冷停堆状态过渡的过程中进行应急停堆盘运行试验;在返回到冷停堆状态后以及安全注射试验后在对反应堆冷却剂进行翻化的过程中,检测蒸汽发生器二次侧可能存在的翻,以判明一、二次侧之间是否存在泄漏。